Epic Summary
Historical coordination record for the original agent-restructuring plan: 111 tasks across ten phases, including 58 originally described as parallelisable. The plan was superseded by #3464; this issue is closed as not planned, not as proof of implementation.
Linked Child Issues/Stories/Tasks/PRs
Milestones & Timeline
Original plan: setup T001–T008; foundations T009–T017 (the original blocker); broken references T018–T032; folder structure T033–T044; skill deduplication T045–T057; skills registry T058–T069; agent registry T070–T082; restructuring plans T083–T093; script migration T094–T102; polish T103–T111. The 30-day plan and eight-day MVP were estimates, not verified delivery dates.
Acceptance Criteria
Dependencies / Blockers
Original foundational phase blocked later stories. Its bespoke seven-item agent folder convention is superseded by decisions under #3464; #3466 owns revision of spec 014. Do not execute this closed checklist as the current plan.
Additional Context
Historical decisions included {category}/{scope}-{title} skill naming, context-dependent Jest/Bats/Playwright testing and a generated JSON registry. These are historical, not automatically current standards.
Definition of Ready (DoR)
Definition of Done (DoD)
Epic Summary
Historical coordination record for the original agent-restructuring plan: 111 tasks across ten phases, including 58 originally described as parallelisable. The plan was superseded by #3464; this issue is closed as not planned, not as proof of implementation.
Linked Child Issues/Stories/Tasks/PRs
.github/specs/014-agents-restructure-consolidate/spec.md..github/specs/014-agents-restructure-consolidate/..github/specs/014-agents-restructure-consolidate/tasks.md.Milestones & Timeline
Original plan: setup T001–T008; foundations T009–T017 (the original blocker); broken references T018–T032; folder structure T033–T044; skill deduplication T045–T057; skills registry T058–T069; agent registry T070–T082; restructuring plans T083–T093; script migration T094–T102; polish T103–T111. The 30-day plan and eight-day MVP were estimates, not verified delivery dates.
Acceptance Criteria
Dependencies / Blockers
Original foundational phase blocked later stories. Its bespoke seven-item agent folder convention is superseded by decisions under #3464; #3466 owns revision of spec 014. Do not execute this closed checklist as the current plan.
Additional Context
Historical decisions included
{category}/{scope}-{title}skill naming, context-dependent Jest/Bats/Playwright testing and a generated JSON registry. These are historical, not automatically current standards.Definition of Ready (DoR)
Definition of Done (DoD)